TPG - Blog Neu

Free Milestone Trend Analysis for MS Project

Written by Steffen Reister | 11.11.2026

In this article, you will learn how to create a Milestone Trend Analysis, what the MTA as a tool visualizes, how to read the chart and what benefits you can draw from it. In addition, we explain where to find a free MTA for Microsoft Project and how to install and use it step by step.

What you will learn about Milestone Trend Analysis in the chapters of this article:


Milestone Trend Analysis: A Combination of History and Forecast

The Milestone Trend Analysis is an easy-to-read combination of history and forecast for selected project milestones. It is used to graphically illustrate time-related discrepancies and helps project managers control projects.

The MTA supports the project manager in controlling the project by:

  • Providing simple reports with easy-to-read charts
  • Revealing deadline bottlenecks in early phases of the project thanks to a clear trend overview
  • Enabling a realistic forecast of the project progression

Explanation of the Milestone Trend Analysis Chart

In an MTA chart, you present the project period on the vertical axis and the reporting period on the horizontal axis. At the beginning of the project, each milestone is displayed on the vertical axis. The earlier the deadline of a milestone, the lower it will be placed on the vertical axis.

If you regularly update the project plan and also save the status of the upcoming milestone, you will get the familiar MTA curves due to the milestone shifts in the course of the project. In this context, the lines indicate the following:

  • A horizontal line means that the milestone date has not changed compared to the previous reporting period
  • In the case of a decreasing line, a milestone has been brought forward and is now scheduled for earlier
  • An increasing line indicates a shift to the future and represents a delay in schedule.
Explanation of the structure of a milestone trend analysis and how to read it

Important note: If you create a Milestone Trend Analysis, it will merely represent a history of past reporting periods. It is entirely at your discretion as a project manager to derive the forecast for the future development of the milestone trend.

Yet even the analysis of the past can be extremely helpful for identifying milestones at a glance that have shifted frequently. These shifts will impact the end of the project sooner or later, if you, as the project manager, do not take timely action to offset the schedule delay.

Thus, you can use the MTA as your perfect early-warning system for scheduling.

Creating a Milestone Trend Analysis for MS Project

TPG The Project Group provides a Milestone Trend Analysis for MS Project (Standard / Professional Client) as a free add-in. You can download your free TPG Milestone Trend Analysis here.

Please, make sure you download the right bit version. Your MS Project bit version is what is relevant in this case (not the Windows version!): for example, select TPG MTA Client in 64 bit, if your MS Project is installed with 64 bit.

 

How to Install the Free TPG MTA for MS Project

  1. Download the file
  2. Start the installation
  3. Once you start your MS Project Client after the installation, you will see a new tab
  4. If this is not the case, please check whether you installed the right bit version corresponding to your MS Project system

 

How to Create the First Project Snapshot

  1. Click Show in the ribbon The Project Group
  2. Click Save in the dialog window TPG MTA 2019
  3. Confirm the creation of the dataset of reports by clicking Yes
Accessing the TPG MTA within the MS Project Client (The Project Group tab)

As a result, the dataset you saved will be displayed.

Saved dataset at the start of the project

By clicking Chart, you can display the MTA chart. At the beginning of the project, each milestone is displayed on the vertical axis.

MTA chart at the beginning of the project

Below, we continue the example we began:

Two weeks later, we are saving the current planning status to the Milestone Trend Analysis tool after updating the project plan. During the reporting period, changes were made to the schedule, but no milestones were shifted. This can be determined from the horizontal lines for the last reporting period.

Reporting period without milestone shifts

Two weeks later, we are saving the current planning status to the Milestone Trend Analysis tool once more after the project plan has been updated. During the reporting period, there have been changes to the schedule which have affected the milestones.

Looking for an introduction to Microsoft Project? Read MS Project Tutorial.

 

This can be determined from the increasing lines for the milestones MS Requirements specified, MS Planning completed, MS Executing / Controlling completed and MS End Project for the last reporting period. In addition, the MS Requirements specified and MS Start Project milestones have been completed; therefore, they are displayed on the 45-degree line.

Reporting period showing delays

At the time the MTA data was saved, there was a shift of the milestones that were not yet completed. At this point in time, the end of the project was likewise postponed.

No later than now, project management should take measures to reduce the risk of further delays and avoid jeopardizing the project.

In the following 2 weeks, an adjustment was made to the project before the MTA data was saved again. This can be determined from the decreasing lines:

Change in planning: reporting period with milestones moved forward

When the MTA data is saved from this point onwards, all connecting lines of the last reporting period lead into the 45-degree line. This makes it clear that all milestones have been completed.

The project manager in this example has succeeded in making up for the delay by the end of the project.

Completed project

Prerequisites for Meaningful Results from the MTA

Please note that the MTA can only provide meaningful information, if the data is always up to date. This will only be the case if you have updated the schedule for all tasks and especially milestones before the creation of a snapshot.

In this way, the MTA can also contribute to a greater awareness of the schedule among project participants.

Note: Thanks to the straightforward graphical overview, a Milestone Trend Analysis can contribute to a greater awareness of the schedule among project participants.

Working MS Project? Read article about Earned Value Analysis with MS Project.

Conclusion: Creating a Milestone Trend Analysis for MS Project

In this article, you have learned how to create the Milestone Trend Analysis and use it for project control. It enables you to identify potential delays in good time and take countermeasures.

Using the free TPG Milestone Trend Analysis for Microsoft Project as an example, you have learned how to collect data for the MTA chart and how to interpret the chart.

Our final tip: Sign up for our bi-weekly blog newsletter with information on more practical articles, eBooks, etc. to improve your project management maturity level.

Do you have any questions? We look forward to hearing from you via the contact form or another channel.