If you are working on the PMO, you may also have to help manage the project portfolio. In this case, the preparation of project portfolio meetings should be one of your key tasks. As a rule, high-level employees will be among the participants.
Therefore, it is important to prepare this regular multi-project management meeting well, conduct it in a focused manner and keep it short while using PPM project tools to produce concise dashboards and summaries. After the meeting, the participants must feel they have been thoroughly briefed and were able to make informed decisions in all cases on the agenda.
In a nutshell: in your position as the PMO, you demonstrate to all participants in the project portfolio meeting that you are in full control of the project landscape. In this article, you will learn how to proceed:
Let us start with the definition of the term project portfolio meeting.
Definition Project Portfolio Meeting:
The project portfolio meeting is a meeting recurring at regular intervals addressing all projects in the multi-project landscape as a whole. The meeting enables participants to make important decisions furthering good management of the project landscape.
For the PMO, the challenges of the project portfolio meeting consist in the following:
The TPG “PPRM Paradise” can help you with these PMO responsibilities.
The top-level portfolio reports are fed from a project list stored in a central database. It is connected to a resource pool. Underneath, you find the methods for individual project management, which automatically fill the project list with information, such as, for example, the traffic light colors.
The coordination of resources between project managers and team leaders is likewise part of this, as is the integration with accounting for forecasts, payment milestones and other questions of finance.
Filterable reports allow the user to get from the project list into the individual projects concerned, e.g. in the case of red traffic lights. This will give you an insight into the reasons for the comment (see red arrows in the graphic).
With such an integrated solution as a multi-project management success factor, you can present the important information to people who have little time and inform them well.
Who exactly participates in the meetings depends on the objectives of the meeting and the requirements of the organization. And here is what you should bear in mind:
Our tip: Keep the group of participants rather small, no more than 5, at most 10 people. If you invite people several times, it may become difficult to disinvite them later to return to the original size of the circle.
You should adjust the group of participants where necessary depending on the topics you will discuss. The smaller the company, the more likely it is that top management will be taking part as well. In larger companies, the heads of department are the more likely participants.
Participants in the case of development projects could be as follows:
Participants in the case of customer projects could be as follows:
The project portfolio meeting must occur on a regular cadence, which is specified by the PMO.
In most cases, the employees will report their actual hours at the end of the week. They will be the basis of the project managers’ weekly status meetings – which in turn provide the basis of the bi-weekly resource meetings between project managers and team leaders. The project portfolio meeting may follow after this. Decisions that cannot be made here need to be made in additional meetings directly after.
The rhythm is key! After all, this is the only way the team will get used to the regular procedure.
Not everything necessarily has to be decided at once. Questions of resource management in particular can only be decided sensibly if there is a sound basis. This is only the case at certain points in the cadence at which all necessary information for the resource decisions is available and up to date.
Our tip: If requests for resources come in out of sync with the cadence, point out that the cadence should be respected and refer to the upcoming project portfolio meeting. In the context of that meeting, the relevant decisions will be made in a way that is sensible from the perspective of the entire project portfolio.
One of the most important responsibilities of the PMO is to ensure reliability in the context of the project portfolio meeting. Yet, this will only work in sync with the cadence. Please pay attention to the following important points:
A survey in our (German-language) webinar on project portfolio meetings revealed that nearly 50% of the almost 100 participants hold monthly project portfolio meetings. However, as mentioned above, the best cadence depends on the individual need at your company.
The most important, urgent and interesting has to go into the agenda of the project portfolio meeting. Roughly, this can include:
Our tip: Make sure that at least the project managers, and possibly also the team leaders, will be informed about successes and important decisions from the meeting after every portfolio meeting (new projects, sales pipeline, great project statuses, hurdles overcome, etc.). This will help prevent unchecked office grapevine.
The project portfolio meeting is where you make all decisions exceeding the competencies of the project managers, sponsors, steering committees and team leaders.
These could be:
To keep your meeting as concise as possible and be able to address the key topics precisely, the preparation provides an important ongoing task for the PMO.
To fulfil this task, you require the regular reports of the project managers resulting from their project work. It is your role as the PMO to ensure data quality and check this with the project managers if necessary. On this basis, you prepare the meeting taking into account any newly added projects and strategic questions.
If the project managers’ information procurement takes too long, it is also the task of the PMO to improve the environment by providing assistance (e.g. coaching, better tools and methods).
As a rule of thumb, the status update for average projects should not take project managers longer than 2-3 hours per project.
Description of the above illustration: Assuming the project portfolio meeting is on a Wednesday, there should be a meeting with the team leaders directly before to clarify the current resource situation. You need to make sure that progress reporting and time tracking have taken place the Friday before. On Monday, there will be a reminder to employees who are running late. Thereupon, the project managers update and check their projects. On Tuesday, project managers who are running late receive a reminder to perform their updates.
Our tip: In any case, set an early date for the editorial deadline for the preparation of the meeting. This will prevent last-minute changes that could destroy your preparation. Those who deliver later are to be classed as tardy employees.
In a TPG webinar, the participants responded as shown in the illustration below regarding the duration of their project portfolio meeting: the majority (almost 50%) responded that it took “2 hours” and 25% responded “1 hour”.
Combined with the survey above, it would appear that the majority of companies conduct one two-hour project portfolio meeting per month.
An up-to-date project list is indispensable for a good project portfolio meeting. It consists of information from the individual project status reports.
The information from the project status reports in the multi-project environment should be automatically entered into the project list. From the list, you can create multi-project reports at the push of a button and exchange data with the ERP system, e.g. via SAP integration.
All of this is possible with the “PPM Paradise” for instance, which we described above.
The figure below shows what important pieces of information you should summarize in a project list.
Please note: Numbers are only one element of the report. A second part that is particularly important is the project manager’s comment. This enables the PMO and the participants of the project portfolio meeting to better understand the classifications for the traffic lights, etc. After all, different individuals can set these in very different ways (you will find a difference here between experienced and inexperienced project managers).
Moreover, the column with the date on which the project data was last published / saved is central to make sure the data presented from each project is truly up to date.
What should you pay attention to, if you want to make sure the project list is up to date? A few tips for you:
Our tip: Set a baseline at the beginning of the project. And create another baseline after each project portfolio meeting. This allows you to see the change from the last meeting. You will not need more than these two baselines.
As mentioned above, you should attach great importance to the editorial deadline to make sure a tardy project manager’s update cannot change the data for your presentation.
By historizing the project list after the editorial deadline, you freeze the respective status of your report for the project portfolio meeting and can always come back to it as required.
Our tip: Use solutions that allow you to automatically create your reports in Excel, PowerPoint or Word in your corporate design. Thus, you make sure the logo is always in the same place and the colors are correct. What is more, the reports are easy to present and print and historize. In most cases, online tools are not as reliable for this purpose. Find a few examples of PMO Reports here.
There are no universal criteria for the importance of projects. Possibilities for the selection could include:
Make sure that the participants give you feedback at the end of your project portfolio meeting. This is easiest with a star rating. Anything under 4 stars must be explained.
On the one hand, such a rating enables you to improve in a goal-orientated manner. On the other hand, good feedback over time provides you with an important basis for proving the benefits of your PMO.
Should anyone question the usefulness of your PMO, good ratings will allow you to prove how satisfied the stakeholders have been with your work so far. Hence, the PMO cannot be useless.
In this article, you have learned what is relevant for a successful and regular project portfolio meeting. As the PMO, you will be successful if all participants perceive this meeting of yours as very valuable. This involves, for example:
The project portfolio meeting is your chance to shine as the PMO enabling you to increase acceptance considerably. Good speed!