Are you planning a professional resource planning implementation to quickly optimize your planning, identify and resolve conflicts in good time? If so, this article is just right for you. The following practical tips should allow you – for instance in the role of PMO – to quickly reach your goal.
The following chapters are waiting for you:
Let us delve in.
Project resource management is often regarded as complicated because:
In addition, it is often assumed that you can only allocate projects and activities properly if you have an overview of who is working on what, and when. Many believe you need sound project planning first of all, but this is not correct!
You can also start by implementing proper resource planning using the approach via the team leaders. And this does not have to be complicated, if you proceed as described below. In our experience, you could even reach your goal in around two months.
The figure below reveals the difference in implementation time between starting with the team leaders and starting with the project managers. You will reach your goal much faster with the overall planning of the resources by the team leaders. The detailed resource planning from the projects, albeit incomplete in total, takes considerably longer.
What is the reason for this striking difference? Among the most important causes are the following:
For these reasons, it will take many months to reach the desired situation. Eventually, you will get an overview of the resource utilization from the overall planning of many project managers. Yet even this overall planning will only include project activities. Operations and absences, which also reduce the capacity, are not taken into consideration.
This means that the resource utilization is still far from complete with the approach via the project managers. Yet, this is exactly what matters. For only a complete resource overview is useful. And this you can easily obtain from the team leaders.
You can start complete resource planning in your teams any time. Besides absences and operations, you should consider all projects at least roughly at the highest level.
Even without knowing the details at the level of tasks, you should be able to assign people to projects with a share of hours per month.
Our tip: A resource overview is only useful when it is complete. The team leaders can actually provide one easily. This is what you should begin with when implementing resource planning.
As a rule, team leaders know what the members of their team are working on. At the very least, they know:
They may not always know the details, but their knowledge of the employees’ activities is comprehensive.
Without an adequate overview, the team leader will not be able to explain the team’s workload. For instance, he or she will struggle to clarify why a new project request will not fit into the team’s current resource utilization. All the same, this tends to be one of the key reasons for implementing resource management in the first place.
To respond to questions of availability, team leaders do not need perfect and detailed planning. Chiefly, they require a complete overview of all resources and their respective activities. The team leader gains a lot by having more or less accurate answers to these questions. This is significantly better than a wrong answer.
It is a great but avoidable mistake to make commitments which cannot be kept. The usual reason is that activities were neglected when calculating the workload.
Apart from that, the team leaders’ planning almost always fluctuates except for vacation and a few regular meetings. After all, it is usually based on estimates.
The key difference lies in this: are you surprised that team members do not have time?
Therefore, the primary objective is not necessarily perfect resource planning. What you need is complete resource planning. Resource planning only begins to be useful once it is complete. The initial complete plan can be refined in further steps.
Later, you can mainly improve one thing: the regular and increasingly more specific coordination with the project managers. The rest lies in the team leaders’ responsibility anyway. And soon it will also be available in the right system.
Our tip: What you require first is complete, not perfect, resource planning. It only begins to be useful once it is complete. Missing details can be added later.
So much for the background. Now, you will learn how to approach resource planning implementation via the team leaders.
If you want to persuade the team leaders, you need to highlight the benefits of a central system for resource planning as follows:
Do some marketing for the resource planning implementation! Get the affected people involved. But watch out: be aware that you are also creating a transparency some team leaders may not be comfortable with.
Another important point is to reach an agreement with the employee organization / works council at an early stage, as they might suspect the possibility of unjustified surveillance of the employees. However, this should not cause any real problems, since:
Our tip: Turn affected people into proponents. Thus, they will support you in advocating the implementation of a solution for tactical resource planning. And be aware that not all team leaders will appreciate this new transparency.
If changes are due, consider first: what has worked well in which area so far? What have team leaders been planning to date? And with how much detail?
Find out the team resource planning methods and data that have been tried and tested and adopt them.
Identify a known well-organized team. And make sure its team leader is willing to support your undertaking and team resource planning methods. You need a template that can be used by everyone. Ideally, you will not start by creating this template in Excel. Instead, use suitable team management software for team leaders. In this way, you point your colleagues in the right direction from the get-go.
Define the planning granularity in weeks or months. Planning in quarters tends to be too rough; days are usually too detailed. This mostly depends on the duration of tasks and the planning intervals.
Should you plan in hours, days or FTEs (Full Time Equivalents)? This is also determined by the scope of the tasks. It may be better to enter the number of days than several hundred hours.
Wondering how resource planning works? Find a few answers in our
Project Resource Management article.
On the other hand, hours are always without ambiguity. In the case of part-time employees, days can raise the question of how these are to be understood. FTEs are an attempt at bypassing this question. The concept needs to be explained all the same.
As repeatedly stated, mind the completeness of the activities more than the specificity. It is much more important to get an approximate overview of which projects are actually being worked on.
But it is problematic to plan individual tasks in detail for some projects while others are not considered at all. Simply because some details are missing.
The point is to record everything to begin with. Thus, you obtain a complete picture, albeit your first draft.
Our tip: Mind the completeness of the recorded activities more than the specificity of your planning. It is important to obtain a complete picture for a start. Otherwise, your planning will contain an unknown quantity of error. This is not conducive to reliable resource planning.
Based on this, you can establish coordination processes with the project managers. Thus, they stand on a better footing from the outset.
There is no need to involve all project managers at once. This can happen step by step. Some projects are about to be completed. Planning them in detail is not worth the effort. Others may only start in a few months. In both cases, rough planning is sufficient. This can be because detailed planning may not be worth pursuing:
But one thing is always wrong: not to plan something only because it cannot be as specific as you would like it to be.
Present the result to the other team leaders and integrate their feedback. After all, each person must:
Before defining the processes, ensure that the team leaders involved become familiar with:
Of course, you can also define the planning intervals first. And begin to populate the tool afterwards.
But in our experience, organizations tend to take on more than they can actually accomplish. That is why it often makes sense to let all team leaders gather experience with the initial planning for their team. Only then, do you define the intervals at which you update the planning.
A good tool for team planning must be a simple one. Normally, a team leader should not need to spend more than two hours per week on team planning.
But the initial planning is bound to take longer because the users must:
In addition, various data will not be as readily available as hoped-for.
Ensure that the team leaders have good support. Planning has to be a positive experience for them from the start. Some will require more support than others will.
It is vital to convince as many team leaders as possible in the first round. They need to recognize the benefits of working with their own real data.
Our tip: At all events, ensure good support for the team leaders in the first few weeks. For them, planning must be a positive, smooth experience without difficulties from the start. And never stop communicating the benefits of working with your own data.
Define steps to be completed when entering the data. The following entries are necessary:
Choose the update frequency that seems reasonable to you. Maybe, you start with a weekly interval. Thus, you might obtain an initial overview of all teams showing the current status consistently.
Naturally, it will include overload yet to be resolved. However, you can only work this out together and at the intervals you determine. Next, it is necessary to coordinate the planning intervals. All involved must be able to comply with them.
As mentioned above, we strongly advise you to introduce a regular process cycle at your company. And this has to be lived. For the requests from projects tend to change dynamically. But the team leaders cannot reschedule their team planning every day.
Therefore, it is necessary for the planning to be up to date by the due date. In the case of resource conflicts, all team leaders and project managers involved have the same current basis for decisions.
You should still get used to the fact that resource planning cannot always be 100 per cent specific. External interferences often come sooner than you can adjust your planning.
This is how you approach the introduction of regular planning intervals:
Interested in the strategic side of resource planning? Read about Capacity Planning.
The figure below shows such a process cycle across the levels of the roles involved.
You may also like our article on capacity planning tools.
Run through the planning cycle a few times. Once it is more or less stable, you can start optimizing it. What is the situation at your company at this point in time?
The following results are likely:
The task at hand is to strike a balance between effort and benefit and optimize it. This can take several weeks or even months.
You could even implement some technical interfaces. These would enable you to synchronize data regarding capacities and absences automatically from HR systems. Or you may automate the interfaces between project planning and team planning using the appropriate integration middleware.
Up to now, you have advanced resource planning on the team leaders’ side. This has allowed you to achieve a complete overview of the workload and availability of team members quickly. Now you need to advance the processes, methods and tools for project planning. The PMO is responsible for doing this.
If you are interested in this part you might want to download our free PMO Survey.
And one final note: Our extensive PMO Survey 2020 came to an interesting conclusion based on the feedback from 330 companies. The lack of transparency in resource planning is one of the top 4 obstacles to greater PMO acceptance. The approach described above may be a good remedy for this.
In this article, you have learned how to approach resource planning implementation and that this can even be a fast process. Choose the approach via the team leaders. They already have a lot of current and important information that needs to be consolidated.
This assumes that you stick to the proposed “basic rules” when implementing resource management. Use the 6 steps described above as a guide to resource planning implementation.
However, always bear the following in mind: the goal is not perfect but complete resource planning. This will provide the basis to make it work for you, too.
Our final tip: Sign up for our bi-weekly blog newsletter with information on more practical articles, eBooks, etc. to improve your project management maturity level.
Do you have any questions? We look forward to hearing from you via the contact form or another channel.